Installation guide

Chiller Installation Guidelines and Commissioning Checklist

Most early chiller problems come from the installation and not from the machine. This guide walks through location, foundation, piping, electrical work, flushing and start-up, with checklists you can print and sign off.

Teqtive process engineering team · 2026-11-24

A chiller should be installed on a level, rigid foundation with clear airflow or condenser water, piped with a strainer, isolation valves, flexible connections, flow switch, air vents and expansion tank, and connected to a correctly sized and earthed power supply. Before the first start the loop must be flushed, filled, vented and proven for flow, and at start-up a full set of readings is logged as the baseline. The sections below give the detail and the checklists.

Always work to the manufacturer's installation manual and general arrangement drawing for your model. The values here are typical practice and do not replace them.

1. Location and clearances

  • Air cooled chillers belong outdoors or on a roof, with open space on every coil face and nothing above the fans. A typical allowance is 1–2 m on coil and service sides. A shed roof, a boundary wall or another chiller placed too close causes hot air to recirculate, and the unit will trip on high pressure in summer.
  • Keep air cooled units away from boiler flues, exhaust fans and sources of dust or fibre.
  • Water cooled chillers go in a ventilated plant room with space to pull condenser and evaporator tubes for cleaning, and headroom for lifting.
  • Keep the chiller as close to the load as practical to limit pipe heat gain and pump head.

2. Foundation and vibration isolation

  • Use a level RCC plinth or structural steel frame designed for the operating weight, which includes the water in the evaporator and tank.
  • Raise the plinth, commonly 100–150 mm above finished floor, so water does not stand under the base frame.
  • For roof installations have a structural engineer confirm the slab or beam loading and place the unit over columns or beams.
  • Fit rubber or neoprene pads for scroll and screw packages on grade. Use spring isolators on roofs and near occupied areas, as the manufacturer recommends.
  • Lift only from the marked lifting points and check level in both directions after placing.

3. Chilled fluid piping

ComponentWherePurpose
Y-strainer, about 20–40 meshEvaporator inlet, and condenser water inlet on water cooled unitsStops weld slag and scale blocking the heat exchanger
Isolation valvesInlet and outlet of chiller, pump and strainerAllows service without draining the loop
Flexible connectionsAt chiller and pump nozzlesStops vibration and pipe strain reaching the unit
Flow switch or differential pressure switchEvaporator outlet, in a straight runStops the compressor if flow fails; prevents freeze-up
Pressure gauges and thermometersInlet and outlet of evaporator and condenserLets you verify flow and heat transfer
Automatic or manual air ventsEvery high pointRemoves trapped air that cuts flow
Expansion tankPump suction side of a closed loopAbsorbs volume change with temperature; holds positive pressure
Balancing valveChiller outlet or branch linesSets design flow
Bypass lineAcross the evaporatorUsed during flushing; kept closed in operation
  • Support all pipework independently. No pipe weight should hang on the chiller nozzles.
  • Size pipes for a water velocity of roughly 1–2.5 m/s to limit pressure drop and noise.
  • Make sure the loop holds at least the minimum water volume stated by the manufacturer, or add a buffer tank, so that the compressor does not short-cycle.
  • Insulate chilled lines with closed-cell insulation and a continuous vapour barrier. For sub-zero glycol and brine lines use greater thickness, seal every joint, and insulate valves, flanges and pump bodies. Any gap will collect ice.

Worked example: checking design flow

For a 30 TR chiller cooling water by 5 °C: heat load = 30 × 3,024 = 90,720 kcal/h. Flow = 90,720 ÷ 5 = 18,144 litres per hour, about 18.1 m³/h or 5.04 litres per second. In a pipe of 65 mm bore (area 0.0033 m²) the velocity is 0.00504 ÷ 0.0033 = about 1.5 m/s, which is within the usual range. At commissioning, a 7 °C drop at full load instead of 5 °C would mean flow is only 5 ÷ 7 = 71 % of design. The load calculation itself is explained in how to calculate chiller tonnage.

4. Condenser water piping (water cooled units)

  • Fit a strainer, isolation valves, flexible connections, gauges and thermometers as on the chilled side.
  • Check that the tower is sized for the chiller's total heat rejection, which is the cooling load plus compressor power, at the site wet bulb. See cooling tower vs chiller.
  • Arrange water treatment and blowdown from day one. Scale forms fastest in the first hot season.

5. Electrical

  • Size the feeder cable and breaker for the maximum running current and starting current on the nameplate.
  • Confirm voltage at the chiller terminals is within the nameplate tolerance, typically ±10 %, with phase imbalance typically under 2 %.
  • Check phase sequence before the first start. Scroll and screw compressors are damaged by reverse rotation.
  • Provide two separate earth connections to the panel and frame as per local electrical rules.
  • Wire the pump interlock and flow switch as shown on the drawing, and re-tighten all power terminals after transport.

6. Flushing and filling

  1. Open the evaporator bypass and close the evaporator isolation valves, so that debris does not enter the heat exchanger.
  2. Circulate clean water through the whole loop for several hours, then drain from low points and clean the strainers. Repeat until the strainer stays clean.
  3. Open the evaporator, close the bypass and fill with treated water or the specified coolant.
  4. Vent air from every high point with the pump running, then top up.
  5. For glycol or brine, premix to the specified concentration and verify with a refractometer after circulating.

Glycol example. A loop holding 1,200 litres that needs 30 % glycol by volume takes 1,200 × 0.30 = 360 litres of glycol and 840 litres of water. Use inhibited industrial glycol and never automotive antifreeze. The concentration must give a freezing point safely below the lowest evaporating temperature; the values are in chilled brine temperature range.

7. Pre-start checklist

CheckAcceptance
Transport damage, oil stains, loose fittingsNone; refrigerant holding pressure in each circuit
Clearances and foundation levelAs per drawing; unit level both ways
Loop flushed, filled and ventedStrainer clean; no air noise at pump
All service and isolation valvesOpen; bypass closed
Pump rotation and currentCorrect direction; current within nameplate
Flow through evaporatorAt design; pressure drop matches data sheet
Coolant concentration (if glycol or brine)As specified, by refractometer
Supply voltage, imbalance, phase sequenceWithin limits; sequence relay healthy
Earthing and terminal tightnessComplete
Crankcase heatersEnergised for the period in the manual, commonly 8–12 hours or more
Compressor oil levelWithin sight glass marks
Safeties: flow switch, HP, LP, antifreeze, overloadsSet to manufacturer's values and proven
Condenser fans or tower fan and pumpCorrect rotation; tower basin full

8. Start-up readings to log

Run the chiller at steady load for at least 30 minutes before recording. These figures are the baseline for every later fault.

ReadingWhy it matters
Voltage and compressor current, each phaseConfirms loading and supply quality
Suction and discharge pressure with saturation temperaturesShows evaporator and condenser performance
Superheat and subcoolingConfirms expansion valve setting and refrigerant charge
Oil pressure or oil levelCompressor lubrication
Chilled fluid inlet and outlet temperature, and flowGives actual capacity
Ambient, or condenser water inlet and outlet temperatureGives condenser approach
Set points, differentials and safety settingsReference for future adjustment

Actual capacity can be checked from the log: TR = flow (L/h) × temperature drop (°C) ÷ 3,024 for water. Later deviations from these values are diagnosed using the troubleshooting guide and the guide to high pressure and low pressure trips.

9. Handover documents

  • General arrangement, piping and wiring drawings as built
  • Operation and maintenance manual
  • Signed commissioning report with the readings above
  • Factory test certificates and pressure test records, as applicable
  • Refrigerant type and charge, oil type and quantity for each circuit
  • List of set points and safety settings
  • Warranty terms and service contacts

From handover onward, follow the industrial chiller maintenance checklist.

Teqtive installation support

Teqtive supplies installation drawings with each chiller and provides commissioning for its air cooled scroll, water cooled screw and glycol chillers. If you are planning a new installation, share your layout and load details through the contact page and we will advise on location, piping and utilities before the machine arrives.

Frequently asked questions

What are the basic chiller installation guidelines?

Place the chiller on a level, rigid foundation with the clearances shown on the manufacturer's drawing. Fit a strainer, isolation valves, flexible connections, a flow switch, air vents, gauges and an expansion tank in the piping. Support pipes independently, flush the loop before connecting the evaporator, provide correctly sized power and earthing, and insulate all cold lines.

How much clearance does an air cooled chiller need?

Follow the manufacturer's general arrangement drawing. As a typical guide, allow 1–2 metres of open space on each coil face and service side, and keep the area above the fans completely open with no roof or shed. Hot discharge air must not be able to return to the coils, and multiple units need extra spacing between them.

What are the pre-commissioning checks for a chiller?

Confirm the loop is flushed, filled and vented, the strainer is clean, valves are open, and the pump runs in the right direction at design flow. Check supply voltage, phase sequence, earthing, terminal tightness and overload settings. Energise crankcase heaters for the period stated in the manual, check oil level, and prove the flow switch and other safeties.

What type of foundation does a chiller need?

A level reinforced concrete plinth or a structural steel frame designed for the operating weight of the chiller, which includes water and refrigerant. Plinths are commonly raised 100–150 mm above floor level to keep the base dry. Vibration isolation pads or spring mounts sit between the chiller and the foundation, selected for the compressor type and location.

What readings should be recorded during chiller commissioning?

Record supply voltage and compressor current on each phase, suction and discharge pressure, superheat and subcooling, oil pressure or level, chilled fluid inlet and outlet temperature and flow, condenser air or water temperatures, ambient, and all safety and control set points. These readings become the baseline for later troubleshooting.